|
Keeler Bridge
When the L&N Railroad abandoned the
railroad corridor that is now the V&E Greenline, it removed the
railroad trestle at West Creek (behind Woodmont Towers), dividing
the Greenline into separate parts. To walk or bike from one end to
the other, users had to leave the V&E Greenline and detour on
neighborhood streets or walk down a steep path into the creek bed
itself. As a result, very few users ventured beyond West Creek, in
contrast to the other heavily used areas of the V&E Greenline.
A decision was made to harmonize the
West Creek Bridge with the existing Lick Creek Bridge by matching
the bridge décor when possible. It is a combination pedestrian
and equipment bridge. Special care was taken to ensure that the
bridge would withstand foot traffic and mowing equipment. Structural
steel "I" beams were chosen and concrete piers were poured to
provide additional weight bearing capacity. The total weight of
the bridge is 13,000 pounds.
Comm unity partner Keeler Ironworks
donated the construction and installation of the bridge. The bridge
was fabricated at their Presidents’ Island facility, put on a
truck for a journey to the V&E Greenline, and placed in its
permanent position by a giant crane provided as a donation by Barnhart Crane and
Rigging. Installation took place on December 18, 2003.
Quotes from the Commercial Appeal
“We did it because it’s a great neighborhood coming up and it’s
something we can contribute.” (Rob Keeler)
"The pedestrian bridge--nearly 17,000 pounds, 50 feet
long--hung in the air by a crane's straps at 10:30 A.M. Thursday."
"Bridges, it seems, make good neighbors."
Tom Bailey, Jr. "Bridge makes V&E
Greenline whole", Memphis Commercial Appeal, December
19, 2004
Keeler Bridge is named in honor of Rob and Wil Keeler, the
community partners who were responsible for building and installing
the bridge.
The Tennessee Parks and Greenways Foundation provided a planning
grant that paid for the technical work—engineering analysis,
architectural drawings, and City legal requirements. John Sheahan
(left) represented the foundation at the installation.
A
grant from the Eastman Kodak and the Conservation Fund paid for the steel used in the bridge fabrication. The remaining
funding came from
donations by Vollintine Evergreen residents and users of
the V&E Greenline.
Sean Fegette of VECA CDC designed the bridge, worked
with contractors and dealt
with regulatory issues. The V&E Greenline Committee, a
program of VECA CDC, planned the bridge.
The total cash cost of the project
was $14,056—one-third was paid from grants and the rest was
donated by residents
and users of the Greenline. The bridge was also highly leveraged with the labor of volunteers and business
partners.
|